THE ASCENT PARK CONSTRUCTION 2

THE ASCENT PARK CONSTRUCTION 2

Summit Sotheby's International Realty
The Ascent Park City
Construction update

The Ascent is taking shape as concrete foundation walls are progressing on the North East Wing. We are very pleased with how the concrete is turning out, the 12 feet tall panels with the tie holes and smooth finish looks incredible! We are getting ready to place our first set of board formed concrete walls, and also getting ready to place our first slab on grade. The Level 0 parking garage slab on grade will allow us to kick off the suspended slab for Level 1 of the parking garage.


Many of the electrical and mechanical items have been procured and are getting ready to be in transit. Overall, the project is progressing, and we are very happy with the quality of work to date.

Aerial construction site with workers on a concrete foundation surrounded by equipment and safety barriers.
Workers build a concrete foundation in front of a large timber-and-stone residence.
Residential construction site with workers assembling foundation rebar and excavators inside concrete walls.
The Ascent

Work With Us

Having dabbled in various fields of real estate over the years and juggling numerous high-demand projects and developments at once, Keri Holland and the team know the value of hard work, experience, and dedication. Connect with us today!

Follow Us on Instagram