The Ascent is taking shape as concrete foundation walls are progressing on the North East Wing. We are very pleased with how the concrete is turning out, the 12 feet tall panels with the tie holes and smooth finish looks incredible! We are getting ready to place our first set of board formed concrete walls, and also getting ready to place our first slab on grade. The Level 0 parking garage slab on grade will allow us to kick off the suspended slab for Level 1 of the parking garage.
Many of the electrical and mechanical items have been procured and are getting ready to be in transit. Overall, the project is progressing, and we are very happy with the quality of work to date.